In late March, for the first time, fourth-year biotechnology students attended a unique lecture from the leading pharmaceutical company Darnytsya, which has been operating since 1930. Today, every sixth package of medicine on pharmacy shelves in our country is manufactured by Darnytsya, and its product portfolio contains approximately 180 pharmaceutical preparations!
During the meeting, attendees immersed themselves in a 3D tour of the Darnytsya pharmaceutical company, visiting:
1. Infusion solution production.
2. Soft form production.
3. Solid form production.
4. Injectable solution and drop production.
5. Sterile antibiotic production.
The main purpose of the meeting was to familiarize students with the management of pharmaceutical manufacturing projects, which includes the following key stages:
- Project start, namely the compilation of a charter, which is a business document containing all necessary information sufficient for developing project plans and subsequent implementation. This is a kind of project passport, the so-called URS (User Requirements Specification).
- The next stage is the formation of a project team, which includes engineers, operational unit, installation group, production group, maintenance department, and where the project manager is designated, who directs and organizes the team’s work at all stages of the project.
- Development of a conceptual design (CS): preparation of preliminary block diagrams of the main technological processes, creation of preliminary planning solutions, list of main equipment, essentially a draft of the future project.
- Functional design (FS), which includes production plans, planning and architectural solutions, process diagrams and material flows, air flow diagrams, pressure differentials, HVAC operating modes, connections to energy resources.
- An important stage is project qualification (DQ), through which URS, CS, and FS must pass, because if the project does not comply with GMP requirements, then the constructed production facility will not comply either.
- After qualification, a detailed design (DS) is prepared, which includes all drawings and diagrams of our development, specifications for all aspects of the production process, quality control documentation, environmental and energy assessments, safety requirements.
- After all the aforementioned stages, project implementation takes place.
We thank the specialists of the Darnytsya pharmaceutical company for providing valuable and comprehensive information to us, fourth-year students, on the eve of developing and preparing our qualifying thesis.
Students of specialty G21 “Biotechnology and Bioengineering” Kateryna Hvozdets’ka and Anastasiya Onyshchenko BT-4-1